- Ditchfield proposed and delivered a revised culvert installation design that shaved four weeks from the program and delivered the client early access to OC3 for no additional cost;
- Zero reportable incidents
- 73,000 manhours with zero LTI
- Construction of civil works associated with the new Open Cut 3 pit at Moolarben Coal.
- Key scope items included:
- 125m long, 5-cell, 3m diameter CSP culvert across Moolarben Creek;
- 3,500m3 of flowable fill culvert surround
- Two clay lined 100+ML mine water dams;
- 2,000m of rock-lined dirty water drains
- 350,000m3 of cut to fill earthworks;
- 2,000m of new haul road construction;
- 200,000m3 of topsoil stripping

Stratford Mining and Rehabilitation
This follows on from previous contract mining work at Stratford involving 30 million m3 of coal and waste over a 7 year period. Mine Operator