- Construction of civil works associated with the new CHPP Water Treatment Facility. The project included work both inside and outside of the Moolarben rail balloon loop, including regular interaction with live rail operations
- Project completed ahead of programme and below client’s budget cost
- Zero reportable incidents or LTI
- Key Scope included:
- Design and construction of three HDPE-lined brine dams (two with leak detection systems), totalling 120,000m2;
- Continuous work around a live rail balloon loop, including upgrading and HDPE lining a portion on the internal batter;
- Un-signalised rail crossing
- 260,000m3 of bulk earthworks to dams WP19, 20 and 21
- Piped drainage installation;
- Rock-lined open drains;
- Pavement construction and surfacing;
Stratford Mining and Rehabilitation
This follows on from previous contract mining work at Stratford involving 30 million m3 of coal and waste over a 7 year period. Mine Operator